The maintenance steps for the 5 gallon water filling machine at each startup are as follows:

5 gallon water filling machine

  • A. Before each startup, lubricating oil must be added to each moving component once.
  • B. Before production, check whether all moving parts are secure, whether screws are loose or detached, and whether the belt transmission part is abnormal.
  • C. Check if the high-pressure air source, low-pressure air source, power supply, and water source are normal.
  • D. Check whether the emergency stop switches, safety door switches, and protective device detection switches are normal.
  • F. Check if the lamp tube is damaged or broken.
  • G. Check if the pneumatic components are leaking and if the action is sensitive.
  • H. Check if the triplet has abnormal air leakage, is it blocked, and if the water storage capacity of the water cup is too full
  • I. When starting the machine, the motor must be started first, and the heating machine must be started with a delay of 30 seconds to prevent voltage fluctuations.
  • J. The internal hygiene of the filling machine must be cleaned.
  • K. When the machine is running, it is necessary to pay close attention to whether there is any abnormal noise, and to detect it early, stop it in a timely manner, and solve it in a timely manner.
  • L. In case of emergency shutdown due to safety protection, the cause must be analyzed based on the on-site situation, and the problem must be found and resolved before starting the machine.